CONCRETE POST BASES 

6 x 4

  • 3no 6ft s.c.p        @   14.65      =       43.95
  • 1 bag of cement   @    4.88      =         4.88
  • 2 bags of grit       @    3.75       =         7.50
  • Minimum labour                                 72.00
  •                            Total for base        128.33 

6 x 6

  • 4no 6ft s.c.p         @   14.65   =   58.60
  • 1 bag of cement    @     4.88   =     4.88
  • 2 bags of grit        @     3.75   =     7.50
  • Minimum labour                            78.00
  •                           Total for base   148.98 

7 x 5

  • 4no 7ft s.c.p         @   14.97   =   59.88
  • 1 bag of cement    @     4.88   =     4.88
  • 2 bags of grit        @     3.75   =     7.50
  • Minimum labour                            78.00
  •                           Total for base   150.26 
 

8 x 4

  • 3no 8ft s.c.p         @   15.34   =   46.02
  • 1 bag of cement    @     4.88   =     4.88
  • 2 bags of grit        @     3.75   =     7.50
  • Minimum labour                            78.00
  •                           Total for base   136.40 
 

8 x 6 No 1

  • 4no 6ft s.c.p         @   14.65   =   58.60
  • 1 bag of cement    @     4.88   =     4.88
  • 3 bags of grit        @     3.75   =     11.25
  • Minimum labour                            84.00
  •                           Total for base   158.73
 

8 x 6 No 2

  • 4no 8ft s.c.p         @   15.34   =   61.36
  • 1 bag of cement    @     4.88   =     4.88
  • 3 bags of grit        @     3.75   =    11.25
  • Minimum labour                            84.00
  •                           Total for base   161.49
 

8 x 8

  • 5no 8ft s.c.p         @   15.34   =   76.70
  • 1 bag of cement    @     4.88   =     4.88
  • 3 bags of grit        @     3.75   =    11.25
  • Minimum labour                            84.00
  •                           Total for base   176.83
 

10 x 6

  • 6no 6ft s.c.p         @   14.65   =   87.90
  • 1 bag of cement    @     4.88   =     4.88
  • 4 bags of grit        @     3.75   =    15.00
  • Minimum labour                            102.00
  •                           Total for base   209.78
 

10 x 8

  • 6no 8ft s.c.p         @   15.34   =   92.04
  • 1 bag of cement    @     4.88   =     4.88
  • 4 bags of grit        @     3.75   =    15.00
  • Minimum labour                            102.00
  •                           Total for base   213.92
 

10 x 10

  • 12no 5ft s.c.p         @   14.25    =  171.00
  • 2 bag of cement      @     4.88    =     9.76
  • 5 bags of grit          @     3.75    =    18.75
  • Minimum labour                              132.00
  •                           Total for base        331.51
 

12 x 6

  • 7no 6ft s.c.p         @   14.65   =  102.55
  • 2 bag of cement    @     4.88   =     9.76
  • 5 bags of grit        @     3.75   =    18.75
  • Minimum labour                          120.00
  •                           Total for base   251.06
 

12 x 8

  • 7no 8ft s.c.p         @   15.34   =  107.38
  • 2 bag of cement    @     4.88   =     9.76
  • 5 bags of grit        @     3.75   =    18.75
  • Minimum labour                          120.00
  •                           Total for base   255.89

 

12 x 10

  • 7no 6ft s.c.p         @   14.65   =  102.55
  • 7no 4ft s.c.p         @   14.25   =    99.75
  • 3 bag of cement    @     4.88   =    14.64
  • 8 bags of grit        @     3.75   =    30.00
  • Minimum labour                           156.00
  •                           Total for base    402.94